Hulu Terengganu Hydroelectric Dam Project has not yet been named officially but most people call it as Kenyir 2. Some parties have claimed that major floods in Kelantan recently to cause more than 100,000 people became victims of Kelantan Sultan Mahmud Power Station monte gordo 2 stems from this. Really what it says it is? .. Read the facts we need to know about this project ..
Before it .. here is what scattered in several social media like Facebook monte gordo and WhatsApp .. When talk with Loh ... he let me first info I was struck by the description for Tembat River ni. Tembat river BLH I say the budget is 300meter above the water level of the lake kenyir now What mengejutkannnya now on top of this Tembat sg 1 lg dam being built for a new power system .. Loh said the project monte gordo kenyir 2 x prnh I know and we mugkin x prnh know about the project kenyir 2 ni Now kerja2 logging d flow Tembat monte gordo Sg is currently underway simultaneously with the process of felling timber impoundment was done because x want wastage of timber as well have been happening during the project kenyir existing lake now. How many people may be informed regarding this? Hatta any political organization possible x all who know When it comes to heavy monsoon rains that occurred monte gordo around the upstream monte gordo BYK ... who cares abundant water flow will damage the dam that is currently built ... one way is to let the water flow upriver meet ... (Sg. Tembat ended in a mountain-view google map) water is impossible to Tasik Kenyir d lps because it will damage the dam that is currently built in hilir..dan if the water is discharged, then there are two conditions that may occur .. 1) dam kenyir AKN receiving water reservoir circumlocution BYK If this happens then the whole Terengganu will accept fate as Kelantan received skrg 2) wall floodgates monte gordo that is currently monte gordo built would be destroyed by the force of water will cause the loss of millions of dollars. If d search by map google..kita will see Sg Tembat actually contiguous with Kuala Krai, Dabong, Gua Musang, Manik Urai .. Overflowing water kenyir 2 Kelantan mnyebabkn this is a bad fate ... Suhana immediate vicinity of the lake turns into .. Sdmh TNB TNB please bhw Tasik Kenyir x lps air..info it is for the existing lake kenyir ... while kenyir 2 x included in the existing phase kenyir ... kenyir 2 jd yet declared it was considered normal monte gordo river overflows Therefore if we look at the fact TNB..paras lg kenyir lake water far outweigh the danger level .... so the question is why? ... x else x is not is because the upstream water that should trn to kenyir..disekat by the dam lake water 2..dan kenyir kenyir 2 Krn kesedihankulate drown this is what happened just now? .. since the start of this year apply new sanctions collected water means water coming from the dam overflow sdgkn door fully ready yet ... there rakan2 who gave their prediction that the flood was just a normal rainfall dpt x Kelantan river only accommodate a water reservoir BYK x has a thread because Kelantan river as well BYK Rajasthan Before we go further, we must first understand the Kenyir Dam Project 2 there are 2 dam. The main dam of Sg Puah reclaimed land and supporting dam on River Dam Puah ie Tembat River Dam built by konktik. There are 2 types of building dams and both work with different monte gordo purposes. Dam Puah use different ways of cut and fill with Tembat River Dam construction. The dam consists of several main parts. 1-2-Puah Dam Dam spillway Tembat 3-Puah 4-Access Road 5-Swicthyard 6-Urbain House 7-Tunnel Puah -Intake -MAT (Main Access Tunnel) -Tail Race -ECV (Emegency Cable & Ventilation) 8-Tunnel -Transfer Tembat -Access To Outlet.
It is a condition of Puah River Dam on 29th December 2014. The quantity of water has not reached the maximum level as the floodgates of the dam was closed on 01/10/2014. Can google this news because there are ministers who came to officiate. This project is not a secret project, please check on the website of TNB and contractors involved. Possible political people do not know as claimed.
This is the spillway, which was completed in full. Road construction of the dam, spillway is the spillway where the water comes out when the reservoir water in the dam reached its maximum level. Spillway this parched on the date 17.12.2014. Water flowing through the spillway will be entered Tasik Kenyir.
This is the water level in the dam Puah Intake of waterways will enter the turbine generator on 29/12/2014. The water level is still far from achieving maximum reservoir. Approximately 15 meters. For measuring reservoir